blob: 18891c8863dc00a19a568816f57371f3c687e5a9 (
plain)
- @startgantt
- language en
- projectscale monthly zoom 3
- skinparam svgDimensionStyle false
- title Group work
- Project starts 2025-02-03
- -- Structure --
- [Research] starts 2025-02-03 and requires 28 days
- [Planning] starts 2025-02-03 and requires 28 days
- [Development] starts 2025-02-03 and requires 56 days
- [Prototyping] as [proto1] starts 2025-02-03 and requires 28 days
- [Testing] starts at [proto1]'s end and requires 28 days
- [Finalizing] starts 2025-04-01 and requires 28 days
- [Documenting] starts 2025-04-01 and requires 28 days
- [Deploying] starts at [Development]'s end and requires 28 days
- -- Deliveries --
- [Delivery for peer review] happens 2025-03-01
- [Peer review] happens 2025-03-19
- [Project delivery] happens 2025-05-27
- [Exam] happens 2025-06-16
- '-- Guidance --
- '[Projektgruppedannelse] starts 2024-02-01 and requires 3 days
- '[Projektgruppe] happens 2024-02-05
- '[Projektgruppe] happens 2024-04-12
- '[Problemformuleringsoplæg] happens 2024-03-12
- '[Problemformuleringsseminar] starts 2024-03-20 and requires 1 days
- '[Møde om visuel præs.] starts 2024-04-10 and requires 1 days
- '[Midtvejsrapport] happens 2024-04-22
- '[Midtvejseval.] starts 2024-05-05 and requires 3 days
- @endgantt
|